Drawing for BEM - BALCKE-ENGINEERING-METHODOLOGY

USPTO serial 77245132

BEM - BALCKE-ENGINEERING-METHODOLOGY

Reviewed by CopyMark Law Group

Reg. 3707335Status 710
Filing date
Status date
Registration date
Nov 10, 2009
Examiner
KEATING, MICHAEL P
Law office
PUBLICATION AND ISSUE SECTION

What this means

Status 710 means the registration was cancelled because a required Section 8 declaration of continued use was not filed within the deadline (including any grace period). The federal registration is no longer active. Evaluate filing a new application if you still use the mark, or petition if cancellation was erroneous. Consult counsel on remaining common-law rights.

Status 710: Status 710 means the registration was cancelled because a required Section 8 declaration of continued use was not filed within the deadline (including any grace period). The federal registration is no longer active.

Need help with BEM - BALCKE-ENGINEERING-METHODOLOGY?

If you own this trademark, we can monitor new filings and help with USPTO deadlines. If you do not, we can file a new U.S. application.

Current trademark owner
Monitor this mark, or talk with CopyMark about this registration.
Not the owner?
File a new U.S. trademark application, or speak with our attorneys.

Owner

Attorney of record

The USPTO lists this attorney as the applicant's representative for correspondence on this application.

John H. Weber

JOHN H. WEBER BAKER & HOSTETLER LLP1050 CONNECTICUT AVENUE, NWWASHINGTON SQUARE, SUITE 1100WASHINGTON, DC 20036

Goods and services

ClassDescriptionStatusFirst use
007Drying, ventilation and water supply installations for cooling towers, power stations and industrial plants, in particular air and flue gas installations in the nature of heat exchangers being parts of machines, air condensers; structural and replacement parts for the aforesaid goodsSECTION 8 - CANCELLED—
011Cooling, heating, steam generating, drying ventilation and water supply plants, namely, cooling towers, power stations and industrial plants; cooling, heating, steam generating, drying, ventilation and water supply installations for cooling towers, power stations and industrial plants, in particular air and flue gas installations, in the nature of heat exchangers not being parts of machines, fluid coolers in the nature of evaporative fluid coolers and water cooling towers; structural and replacement parts for the aforesaid goodsSECTION 8 - CANCELLED—
037Repair, maintenance and installation services in the field of cooling, heating, steam generating, drying, ventilation and water supply plants, namely, cooling towers, power stations and industrial plants and installations thereforSECTION 8 - CANCELLED—
042Scientific and industrial research, engineering services and technological consultancy, product research, product design, and information technology consultation in the nature of optimization of computer equipment; all the foregoing services in the field of cooling, heating, steam generating, drying, ventilation and water supply plants, namely, cooling towers, power stations and industrial plants and installations thereforSECTION 8 - CANCELLED—

Related trademarks

CopyMark links this record to cited §2(d) serials, the owner's other marks, Nice classes, similar mark names, and recently changed USPTO applications.

Prosecution history

DateCodeEventWhat it means
Jun 17, 2016C8..CANCELLED SEC. 8 (6-YR)—
Nov 10, 2009R.PRREGISTERED-PRINCIPAL REGISTERYour trademark is registered on the Principal Register — the strongest form of federal trademark protection. You may use the ® symbol for the covered goods and services. Maintenance filings (Section 8 and renewals) are required to keep the registration alive.
Oct 1, 2009DP1B1(B) BASIS DELETED; PROCEED TO REGISTRATION—
Oct 1, 2009AITUCASE ASSIGNED TO INTENT TO USE PARALEGAL—
Sep 24, 2009IUCNNOTICE OF ALLOWANCE CANCELLED—
Sep 24, 2009D1BRTEAS DELETE 1(B) BASIS RECEIVED—
Sep 8, 2009NOAMNOA MAILED - SOU REQUIRED FROM APPLICANTA Notice of Allowance means your intent-to-use application cleared examination and opposition but is not registered yet. You must file a Statement of Use showing the mark in commerce, or request an extension, before the deadline — usually six months from the notice date.
Jun 16, 2009PUBOPUBLISHED FOR OPPOSITIONYour mark was published in the USPTO Official Gazette for a 30-day opposition window. During that period, third parties who believe they would be harmed can file an opposition. If no opposition is filed, prosecution usually continues toward registration or a Notice of Allowance.
May 27, 2009NPUBNOTICE OF PUBLICATION—
May 13, 2009ASCKASSIGNMENT OF OWNERSHIP NOT UPDATED AUTOMATICALLY—
May 8, 2009PREVLAW OFFICE PUBLICATION REVIEW COMPLETED—
May 8, 2009ALIEASSIGNED TO LIE—
May 8, 2009CNSAAPPROVED FOR PUB - PRINCIPAL REGISTER—
May 7, 2009TEMETEAS/EMAIL CORRESPONDENCE ENTERED—
May 7, 2009CRFACORRESPONDENCE RECEIVED IN LAW OFFICE—
May 7, 2009TROATEAS RESPONSE TO OFFICE ACTION RECEIVEDThis event means the applicant filed a response to a USPTO Office Action — typically arguments, amendments, or evidence addressing the examiner's objections. The USPTO will review the response and either allow the mark to proceed or issue another action.
Nov 10, 2008GNRNNOTIFICATION OF NON-FINAL ACTION E-MAILEDA non-final Office Action means the USPTO examining attorney has raised at least one issue with your trademark application but has not made a final decision. You usually have three months to respond with arguments, amendments, or evidence. Missing the deadline can abandon the application.
Nov 10, 2008GNRTNON-FINAL ACTION E-MAILEDA non-final Office Action means the USPTO examining attorney has raised at least one issue with your trademark application but has not made a final decision. You usually have three months to respond with arguments, amendments, or evidence. Missing the deadline can abandon the application.
Nov 10, 2008CNRTNON-FINAL ACTION WRITTENA non-final Office Action means the USPTO examining attorney has raised at least one issue with your trademark application but has not made a final decision. You usually have three months to respond with arguments, amendments, or evidence. Missing the deadline can abandon the application.
Nov 6, 2008TEMETEAS/EMAIL CORRESPONDENCE ENTERED—
Nov 6, 2008CRFACORRESPONDENCE RECEIVED IN LAW OFFICE—
Nov 6, 2008ERSITEAS RESPONSE TO SUSPENSION INQUIRY RECEIVED—
Jul 7, 2008GNS2NOTIFICATION OF INQUIRY AS TO SUSPENSION E-MAILED—
Jul 7, 2008GNSIINQUIRY TO SUSPENSION E-MAILED—
Jul 7, 2008CNSISUSPENSION INQUIRY WRITTEN—
Jan 7, 2008GNS3NOTIFICATION OF LETTER OF SUSPENSION E-MAILED—
Jan 7, 2008GNSLLETTER OF SUSPENSION E-MAILED—
Jan 7, 2008CNSLSUSPENSION LETTER WRITTEN—
Jan 3, 2008TEMETEAS/EMAIL CORRESPONDENCE ENTERED—
Jan 3, 2008CRFACORRESPONDENCE RECEIVED IN LAW OFFICE—
Jan 3, 2008TROATEAS RESPONSE TO OFFICE ACTION RECEIVEDThis event means the applicant filed a response to a USPTO Office Action — typically arguments, amendments, or evidence addressing the examiner's objections. The USPTO will review the response and either allow the mark to proceed or issue another action.
Nov 9, 2007GNRNNOTIFICATION OF NON-FINAL ACTION E-MAILEDA non-final Office Action means the USPTO examining attorney has raised at least one issue with your trademark application but has not made a final decision. You usually have three months to respond with arguments, amendments, or evidence. Missing the deadline can abandon the application.
Nov 9, 2007GNRTNON-FINAL ACTION E-MAILEDA non-final Office Action means the USPTO examining attorney has raised at least one issue with your trademark application but has not made a final decision. You usually have three months to respond with arguments, amendments, or evidence. Missing the deadline can abandon the application.
Nov 9, 2007CNRTNON-FINAL ACTION WRITTENA non-final Office Action means the USPTO examining attorney has raised at least one issue with your trademark application but has not made a final decision. You usually have three months to respond with arguments, amendments, or evidence. Missing the deadline can abandon the application.
Nov 8, 2007DOCKASSIGNED TO EXAMINER—
Aug 7, 2007NWAPNEW APPLICATION ENTERED—