Drawing for LEITNER TECHNOLOGIES

USPTO serial 79045691

LEITNER TECHNOLOGIES

Reviewed by CopyMark Law Group

Reg. 3731507Status 404
Filing date
Status date
Registration date
Dec 29, 2009
Examiner
SETTLES LEWIS, SHAILA E
Law office
PUBLICATION AND ISSUE SECTION

What this means

This page summarizes the public USPTO record for this serial number, including owners, goods and services, and prosecution history.

Need help with LEITNER TECHNOLOGIES?

If you own this trademark, we can monitor new filings and help with USPTO deadlines. If you do not, we can file a new U.S. application.

Current trademark owner
Monitor this mark, or talk with CopyMark about this registration.
Not the owner?
File a new U.S. trademark application, or speak with our attorneys.

Owner

Attorney of record

The USPTO lists this attorney as the applicant's representative for correspondence on this application.

Robert F. Scotti

ROBERT F. SCOTTI KLARQUIST SPARKMAN, LLP121 SW SALMON STREETONE WORLD TRADE CENTER-SUITE 1600PORTLAND, OR 97204

Goods and services

ClassDescriptionStatusFirst use
007Machine-operated implements and equipment for land, garden and forestry purposes, in particular for snow piste care, namely, power tillers, plows and snow groomers for maintaining snow pistes, cross country skiing tracks, cross country races, for the treatment of surfaces covered with snow or sand; machine coupling and transmission components except for land vehicles; snow grooming machines and power-operated snow grooming machine accessories, namely, plows, tillers and rakes, and replacement parts therefor; snow making machines, snow making machine accessories, namely, snow blowers and replacement parts therefor; windmills including offshore windmills, wind-powered electricity generators including offshore wind-powered electricity generators, wind turbines and generators for wind turbines; parts and fittings for the aforesaid goods, namely, wind-powered electricity generators frequency converters, electrical generators, electrical motors, electrical controlling devices, towers for windmills, blades for wind turbines, blade hubs for wind turbines, mill housings for wind turbines, rotor blades and rotors, foundations for windmills; yaw rings and gears wind turbines; devices, namely, power-generated toothed wheels for controlling the pitch of the blades, brakes for wind turbines, main shafts for wind turbines, power transmissions and gearing for wind turbines, clutches for machines and electric generators, all the aforesaid goods for windmills and wind power plantsSECTION 71 - CANCELLED—
009Electrical, electronic and computer equipment for windmills, namely, commutators, electric controllers for wind turbines, electrical transformers, power lines, inverters, batteries, capacitors, accumulators, and condensers; electric cables; computer software and electrical circuit closers for automatically turning a generator on or off and for automatic starting after a power line break-down, voltage surge suppressors for protection against high voltage lightning surges, microprocessors for controlling and monitoring constant voltage, frequency, phase conditions and rotor speed, control of the efficiency and thickness of brake pads and of temperature, direction and speed of wind, vibration sensor for installation in windmill housings, electric watt-hour metersSECTION 71 - CANCELLED—
012Aerial ropeway or cable systems, namely, ski lifts, chair lifts, gondola lifts, cable cars, tramways; ground ropeway and cable transport apparatus, namely, funiculars; private and public rail transportation systems, namely, elevated tramways, automatic tramways; replacement parts for tramways; land vehicles, in particular off-road all terrain vehiclesSECTION 71 - CANCELLED—
037Erection, construction, installation, maintenance and repair of windmills and wind power plants; construction and repair of snow grooming machines, snow making machines, aerial ropeway, ground ropeway and public rail transportationSECTION 71 - CANCELLED—
042Technical engineering consultancy concerning technical design and planning of windmill and wind power plants, development and testing of windmills, wind power plants and of components of windmills and wind power plants, conducting research projects concerning windmills; technical planning of snow grooming machines, snow making machines, aerial ropeway systems, ground ropeway systems and public rail transportation systemsSECTION 71 - CANCELLED—
045Legal assistance concerning windmill and wind power plant projectsSECTION 71 - CANCELLED—

Related trademarks

CopyMark links this record to cited §2(d) serials, the owner's other marks, Nice classes, similar mark names, and recently changed USPTO applications.

Prosecution history

DateCodeEventWhat it means
Aug 17, 2017DENCNOTIFICATION OF EFFECT OF CANCELLATION OF INTL REG MAILED—
Aug 17, 2017DETHDEATH OF INTERNATIONAL REGISTRATION—
May 26, 2017INNTTOTAL INVALIDATION PROCESSED BY THE IB—
Apr 8, 2017INTSTOTAL INVALIDATION OF REG EXT PROTECTION SENT TO IB—
Apr 7, 2017INPCINVALIDATION PROCESSED—
Apr 5, 2017INTRTOTAL INVALIDATION OF REG EXT PROTECTION CREATED—
Aug 5, 2016C71TCANCELLED SECTION 71—
Feb 5, 2013FINOFINAL DECISION TRANSACTION PROCESSED BY IB—
Apr 19, 2010FICSFINAL DISPOSITION NOTICE SENT TO IB—
Apr 19, 2010FIMPFINAL DISPOSITION PROCESSED—
Mar 29, 2010FICRFINAL DISPOSITION NOTICE CREATED, TO BE SENT TO IB—
Dec 29, 2009R.PRREGISTERED-PRINCIPAL REGISTERYour trademark is registered on the Principal Register — the strongest form of federal trademark protection. You may use the ® symbol for the covered goods and services. Maintenance filings (Section 8 and renewals) are required to keep the registration alive.
Oct 13, 2009NPUBOFFICIAL GAZETTE PUBLICATION CONFIRMATION E-MAILED—
Oct 13, 2009PUBOPUBLISHED FOR OPPOSITIONYour mark was published in the USPTO Official Gazette for a 30-day opposition window. During that period, third parties who believe they would be harmed can file an opposition. If no opposition is filed, prosecution usually continues toward registration or a Notice of Allowance.
Sep 9, 2009PREVLAW OFFICE PUBLICATION REVIEW COMPLETED—
Sep 9, 2009CNSAAPPROVED FOR PUB - PRINCIPAL REGISTER—
Aug 10, 2009TEMETEAS/EMAIL CORRESPONDENCE ENTERED—
Aug 10, 2009CRFACORRESPONDENCE RECEIVED IN LAW OFFICE—
Aug 7, 2009ERFRTEAS REQUEST FOR RECONSIDERATION RECEIVED—
Aug 7, 2009EXPIEX PARTE APPEAL-INSTITUTED—
Aug 7, 2009JURTJURISDICTION RESTORED TO EXAMINING ATTORNEY—
Aug 7, 2009EXAFEXPARTE APPEAL RECEIVED AT TTAB—
Aug 1, 2009TEMETEAS/EMAIL CORRESPONDENCE ENTERED—
Jul 31, 2009CRFACORRESPONDENCE RECEIVED IN LAW OFFICE—
Jul 31, 2009ERFRTEAS REQUEST FOR RECONSIDERATION RECEIVED—
May 15, 2009OPNXNOTIFICATION OF POSSIBLE OPPOSITION - PROCESSED BY IB—
Apr 30, 2009OPNSNOTIFICATION OF POSSIBLE OPPOSITION SENT TO IB—
Apr 30, 2009OPNRNOTIFICATION OF POSSIBLE OPPOSITION CREATED, TO BE SENT TO IB—
Feb 9, 2009GNFNNOTIFICATION OF FINAL REFUSAL EMAILED—
Feb 9, 2009GNFRFINAL REFUSAL E-MAILEDA final Office Action (final refusal) means the examining attorney is maintaining at least one refusal and your options are narrower. You can file a response addressing the refusal, appeal to the Trademark Trial and Appeal Board, or let the application abandon.
Feb 9, 2009CNFRFINAL REFUSAL WRITTENA final Office Action (final refusal) means the examining attorney is maintaining at least one refusal and your options are narrower. You can file a response addressing the refusal, appeal to the Trademark Trial and Appeal Board, or let the application abandon.
Jan 19, 2009TEMETEAS/EMAIL CORRESPONDENCE ENTERED—
Jan 16, 2009CRFACORRESPONDENCE RECEIVED IN LAW OFFICE—
Jan 16, 2009TROATEAS RESPONSE TO OFFICE ACTION RECEIVEDThis event means the applicant filed a response to a USPTO Office Action — typically arguments, amendments, or evidence addressing the examiner's objections. The USPTO will review the response and either allow the mark to proceed or issue another action.
Jul 18, 2008GNRNNOTIFICATION OF NON-FINAL ACTION E-MAILEDA non-final Office Action means the USPTO examining attorney has raised at least one issue with your trademark application but has not made a final decision. You usually have three months to respond with arguments, amendments, or evidence. Missing the deadline can abandon the application.
Jul 18, 2008GNRTNON-FINAL ACTION E-MAILEDA non-final Office Action means the USPTO examining attorney has raised at least one issue with your trademark application but has not made a final decision. You usually have three months to respond with arguments, amendments, or evidence. Missing the deadline can abandon the application.
Jul 18, 2008CNRTNON-FINAL ACTION WRITTENA non-final Office Action means the USPTO examining attorney has raised at least one issue with your trademark application but has not made a final decision. You usually have three months to respond with arguments, amendments, or evidence. Missing the deadline can abandon the application.
Jun 12, 2008TEMETEAS/EMAIL CORRESPONDENCE ENTERED—
Jun 12, 2008ALIEASSIGNED TO LIE—
Jun 11, 2008CRFACORRESPONDENCE RECEIVED IN LAW OFFICE—
Jun 11, 2008TROATEAS RESPONSE TO OFFICE ACTION RECEIVEDThis event means the applicant filed a response to a USPTO Office Action — typically arguments, amendments, or evidence addressing the examiner's objections. The USPTO will review the response and either allow the mark to proceed or issue another action.
May 30, 2008ARAAATTORNEY/DOM.REP.REVOKED AND/OR APPOINTEDThis event means the applicant filed a response to a USPTO Office Action — typically arguments, amendments, or evidence addressing the examiner's objections. The USPTO will review the response and either allow the mark to proceed or issue another action.
May 30, 2008REAPTEAS REVOKE/APP/CHANGE ADDR OF ATTY/DOM REP RECEIVED—
Dec 29, 2007RFNTREFUSAL PROCESSED BY IB—
Dec 12, 2007RFCSNON-FINAL ACTION MAILED - REFUSAL SENT TO IB—
Dec 12, 2007RFRRREFUSAL PROCESSED BY MPU—
Dec 12, 2007RFCRNON-FINAL ACTION (IB REFUSAL) PREPARED FOR REVIEW—
Dec 11, 2007CNRTNON-FINAL ACTION WRITTENA non-final Office Action means the USPTO examining attorney has raised at least one issue with your trademark application but has not made a final decision. You usually have three months to respond with arguments, amendments, or evidence. Missing the deadline can abandon the application.
Nov 30, 2007DOCKASSIGNED TO EXAMINER—
Nov 30, 2007NWAPNEW APPLICATION ENTERED—
Nov 29, 2007REPRSN ASSIGNED FOR SECT 66A APPL FROM IB—