USPTO serial 85423600
Reviewed by CopyMark Law Group
This page summarizes the public USPTO record for this serial number, including owners, goods and services, and prosecution history.
If you own this trademark, we can monitor new filings and help with USPTO deadlines. If you do not, we can file a new U.S. application.
The USPTO lists this attorney as the applicant's representative for correspondence on this application.
Michael Louie
MICHAEL LOUIE Beyer Law Group LLPP. O. Box 51887Palo Alto, CA 94303-1887UNITED STATES| Class | Description | Status | First use |
|---|---|---|---|
| 009 | Modular data center components and data center modules comprised of power supplies, electrical switchgear, electrical switchboards, electrical distribution boards, electrical controls, electrical power distribution units, electrical cables and electrical connectors, featuring cooling and ventilation components, all of the modules and components of which are integrated with site-built construction | ACTIVE | — |
CopyMark links this record to cited §2(d) serials, the owner's other marks, Nice classes, similar mark names, and recently changed USPTO applications.
| Date | Code | Event | What it means |
|---|---|---|---|
| Jun 1, 2015 | MAB6 | ABANDONMENT NOTICE MAILED - NO USE STATEMENT FILED | The intent-to-use application was abandoned because no acceptable Statement of Use (or valid extension) was filed before the Notice of Allowance deadline expired. The application is dead unless revived within a limited window. |
| Jun 1, 2015 | ABN6 | ABANDONMENT - NO USE STATEMENT FILED | The intent-to-use application was abandoned because no acceptable Statement of Use (or valid extension) was filed before the Notice of Allowance deadline expired. The application is dead unless revived within a limited window. |
| Nov 4, 2014 | DOCK | ASSIGNED TO EXAMINER | — |
| Oct 31, 2014 | EXRA | NOTICE OF APPROVAL OF EXTENSION REQUEST E-MAILED | — |
| Oct 30, 2014 | EX5G | SOU EXTENSION 5 GRANTED | — |
| Oct 27, 2014 | EXT5 | SOU EXTENSION 5 FILED | — |
| Oct 27, 2014 | EEXT | SOU TEAS EXTENSION RECEIVED | The applicant requested more time to file a Statement of Use before the Notice of Allowance deadline. Each extension typically adds six months. A limited number of extensions are available for intent-to-use applications not yet in use. |
| Apr 29, 2014 | EXRA | NOTICE OF APPROVAL OF EXTENSION REQUEST E-MAILED | — |
| Apr 28, 2014 | EX4G | SOU EXTENSION 4 GRANTED | — |
| Apr 23, 2014 | EXT4 | SOU EXTENSION 4 FILED | — |
| Apr 23, 2014 | EEXT | SOU TEAS EXTENSION RECEIVED | The applicant requested more time to file a Statement of Use before the Notice of Allowance deadline. Each extension typically adds six months. A limited number of extensions are available for intent-to-use applications not yet in use. |
| Jan 13, 2014 | TCCA | TEAS CHANGE OF CORRESPONDENCE RECEIVED | — |
| Nov 7, 2013 | EXRA | NOTICE OF APPROVAL OF EXTENSION REQUEST E-MAILED | — |
| Nov 6, 2013 | EX3G | SOU EXTENSION 3 GRANTED | — |
| Oct 30, 2013 | EXT3 | SOU EXTENSION 3 FILED | — |
| Oct 30, 2013 | EEXT | SOU TEAS EXTENSION RECEIVED | The applicant requested more time to file a Statement of Use before the Notice of Allowance deadline. Each extension typically adds six months. A limited number of extensions are available for intent-to-use applications not yet in use. |
| Jun 1, 2013 | NOAC | CORRECTED NOA E-MAILED | — |
| May 31, 2013 | DPCC | DIVISIONAL PROCESSING COMPLETE | — |
| May 3, 2013 | DRRR | DIVISIONAL REQUEST RECEIVED | — |
| May 3, 2013 | ERTD | TEAS REQUEST TO DIVIDE RECEIVED | — |
| May 3, 2013 | EXRA | NOTICE OF APPROVAL OF EXTENSION REQUEST E-MAILED | — |
| May 2, 2013 | EX2G | SOU EXTENSION 2 GRANTED | — |
| Apr 29, 2013 | EXT2 | SOU EXTENSION 2 FILED | — |
| Apr 29, 2013 | EEXT | SOU TEAS EXTENSION RECEIVED | The applicant requested more time to file a Statement of Use before the Notice of Allowance deadline. Each extension typically adds six months. A limited number of extensions are available for intent-to-use applications not yet in use. |
| Nov 6, 2012 | EXRA | NOTICE OF APPROVAL OF EXTENSION REQUEST E-MAILED | — |
| Nov 5, 2012 | EX1G | SOU EXTENSION 1 GRANTED | — |
| Nov 2, 2012 | AITU | CASE ASSIGNED TO INTENT TO USE PARALEGAL | — |
| Oct 30, 2012 | EXT1 | SOU EXTENSION 1 FILED | — |
| Oct 30, 2012 | EEXT | SOU TEAS EXTENSION RECEIVED | The applicant requested more time to file a Statement of Use before the Notice of Allowance deadline. Each extension typically adds six months. A limited number of extensions are available for intent-to-use applications not yet in use. |
| May 22, 2012 | CHAN | APPLICANT/CORRESPONDENCE CHANGES (NON-RESPONSIVE) ENTERED | — |
| May 22, 2012 | COAR | TEAS CHANGE OF OWNER ADDRESS RECEIVED | — |
| May 1, 2012 | NOAM | NOA E-MAILED - SOU REQUIRED FROM APPLICANT | A Notice of Allowance means your intent-to-use application cleared examination and opposition but is not registered yet. You must file a Statement of Use showing the mark in commerce, or request an extension, before the deadline — usually six months from the notice date. |
| Mar 6, 2012 | NPUB | OFFICIAL GAZETTE PUBLICATION CONFIRMATION E-MAILED | — |
| Mar 6, 2012 | PUBO | PUBLISHED FOR OPPOSITION | Your mark was published in the USPTO Official Gazette for a 30-day opposition window. During that period, third parties who believe they would be harmed can file an opposition. If no opposition is filed, prosecution usually continues toward registration or a Notice of Allowance. |
| Feb 15, 2012 | NONP | NOTIFICATION OF NOTICE OF PUBLICATION E-MAILED | — |
| Jan 27, 2012 | PREV | LAW OFFICE PUBLICATION REVIEW COMPLETED | — |
| Jan 25, 2012 | ALIE | ASSIGNED TO LIE | — |
| Jan 6, 2012 | CNSA | APPROVED FOR PUB - PRINCIPAL REGISTER | — |
| Jan 6, 2012 | XAEC | EXAMINER'S AMENDMENT ENTERED | — |
| Jan 6, 2012 | GNEN | NOTIFICATION OF EXAMINERS AMENDMENT E-MAILED | — |
| Jan 6, 2012 | GNEA | EXAMINERS AMENDMENT E-MAILED | — |
| Jan 6, 2012 | CNEA | EXAMINERS AMENDMENT -WRITTEN | — |
| Jan 1, 2012 | DOCK | ASSIGNED TO EXAMINER | — |
| Sep 20, 2011 | NWOS | NEW APPLICATION OFFICE SUPPLIED DATA ENTERED | — |
| Sep 19, 2011 | NWAP | NEW APPLICATION ENTERED | — |