What this means

Status 710 means the registration was cancelled because a required Section 8 declaration of continued use was not filed within the deadline (including any grace period). The federal registration is no longer active. Evaluate filing a new application if you still use the mark, or petition if cancellation was erroneous. Consult counsel on remaining common-law rights.

Status 710: Status 710 means the registration was cancelled because a required Section 8 declaration of continued use was not filed within the deadline (including any grace period). The federal registration is no longer active.

Need help with DATAGRYD MICROGRYD SHELL?

If you own this trademark, we can monitor new filings and help with USPTO deadlines. If you do not, we can file a new U.S. application.

Current trademark owner
Monitor this mark, or talk with CopyMark about this registration.
Not the owner?
File a new U.S. trademark application, or speak with our attorneys.

Owner

Attorney of record

The USPTO lists this attorney as the applicant's representative for correspondence on this application.

Scott Kareff

SCOTT KAREFF SCHULTE ROTH & ZABEL LLP919 3RD AVE FL 22NEW YORK, NY 10022-3905UNITED STATES

Goods and services

ClassDescriptionStatusFirst use
037Real estate development; providing real estate development featuring data center sites with energy-efficient technology infrastructuresSECTION 8 - CANCELLED—
042Providing data center facilities featuring energy-efficient technology infrastructureSECTION 8 - CANCELLED—
045Real estate services, namely, licensing of real estateSECTION 8 - CANCELLED—

Related trademarks

CopyMark links this record to cited §2(d) serials, the owner's other marks, Nice classes, similar mark names, and recently changed USPTO applications.

Prosecution history

DateCodeEventWhat it means
Oct 30, 2020C8..CANCELLED SEC. 8 (6-YR)—
Mar 25, 2019REM1COURTESY REMINDER - SEC. 8 (6-YR) E-MAILED—
Oct 27, 2014CHANAPPLICANT/CORRESPONDENCE CHANGES (NON-RESPONSIVE) ENTERED—
Oct 27, 2014COARTEAS CHANGE OF OWNER ADDRESS RECEIVED—
Mar 25, 2014R.PRREGISTERED-PRINCIPAL REGISTERYour trademark is registered on the Principal Register — the strongest form of federal trademark protection. You may use the ® symbol for the covered goods and services. Maintenance filings (Section 8 and renewals) are required to keep the registration alive.
Feb 18, 2014SUNANOTICE OF ACCEPTANCE OF STATEMENT OF USE E-MAILED—
Feb 15, 2014REGVLAW OFFICE REGISTRATION REVIEW COMPLETED—
Feb 13, 2014CNPRALLOWED PRINCIPAL REGISTER - SOU ACCEPTED—
Feb 11, 2014EXRANOTICE OF APPROVAL OF EXTENSION REQUEST E-MAILED—
Feb 8, 2014SUPCSTATEMENT OF USE PROCESSING COMPLETE—
Feb 8, 2014EX2GSOU EXTENSION 2 GRANTED—
Jan 22, 2014EXT2SOU EXTENSION 2 FILED—
Jan 22, 2014EEXTSOU TEAS EXTENSION RECEIVEDThe applicant requested more time to file a Statement of Use before the Notice of Allowance deadline. Each extension typically adds six months. A limited number of extensions are available for intent-to-use applications not yet in use.
Jan 17, 2014IUAFUSE AMENDMENT FILED—
Jan 17, 2014EISUTEAS STATEMENT OF USE RECEIVEDThe applicant filed a Statement of Use with specimens showing the mark in actual commerce. The USPTO will review the filing for compliance. If accepted, the mark can proceed to registration; if deficient, the USPTO may issue a requirement or office action.
Aug 21, 2013EXRANOTICE OF APPROVAL OF EXTENSION REQUEST E-MAILED—
Aug 20, 2013EX1GSOU EXTENSION 1 GRANTED—
Aug 19, 2013AITUCASE ASSIGNED TO INTENT TO USE PARALEGAL—
Jul 19, 2013EXT1SOU EXTENSION 1 FILED—
Jul 19, 2013EEXTSOU TEAS EXTENSION RECEIVEDThe applicant requested more time to file a Statement of Use before the Notice of Allowance deadline. Each extension typically adds six months. A limited number of extensions are available for intent-to-use applications not yet in use.
Jul 1, 2013DOCKASSIGNED TO EXAMINER—
Jan 22, 2013NOAMNOA E-MAILED - SOU REQUIRED FROM APPLICANTA Notice of Allowance means your intent-to-use application cleared examination and opposition but is not registered yet. You must file a Statement of Use showing the mark in commerce, or request an extension, before the deadline — usually six months from the notice date.
Nov 27, 2012NPUBOFFICIAL GAZETTE PUBLICATION CONFIRMATION E-MAILED—
Nov 27, 2012PUBOPUBLISHED FOR OPPOSITIONYour mark was published in the USPTO Official Gazette for a 30-day opposition window. During that period, third parties who believe they would be harmed can file an opposition. If no opposition is filed, prosecution usually continues toward registration or a Notice of Allowance.
Nov 7, 2012NONPNOTIFICATION OF NOTICE OF PUBLICATION E-MAILED—
Oct 24, 2012PREVLAW OFFICE PUBLICATION REVIEW COMPLETED—
Oct 23, 2012CNSAAPPROVED FOR PUB - PRINCIPAL REGISTER—
Oct 23, 2012XAECEXAMINER'S AMENDMENT ENTERED—
Oct 23, 2012GNENNOTIFICATION OF EXAMINERS AMENDMENT E-MAILED—
Oct 23, 2012GNEAEXAMINERS AMENDMENT E-MAILED—
Oct 23, 2012CNEAEXAMINERS AMENDMENT -WRITTEN—
Sep 12, 2012ZZZXPREVIOUS ALLOWANCE COUNT WITHDRAWN—
Aug 26, 2012PBCRWITHDRAWN FROM PUB - OG REVIEW QUERY—
Aug 13, 2012PREVLAW OFFICE PUBLICATION REVIEW COMPLETED—
Aug 13, 2012CNSAAPPROVED FOR PUB - PRINCIPAL REGISTER—
Jul 26, 2012TEMETEAS/EMAIL CORRESPONDENCE ENTERED—
Jul 26, 2012CRFACORRESPONDENCE RECEIVED IN LAW OFFICE—
Jul 24, 2012TROATEAS RESPONSE TO OFFICE ACTION RECEIVEDThis event means the applicant filed a response to a USPTO Office Action — typically arguments, amendments, or evidence addressing the examiner's objections. The USPTO will review the response and either allow the mark to proceed or issue another action.
Jul 18, 2012CEPECOMBINED EXAMINER'S AMENDMENT/PRIORITY ACTION ENTERED—
Jul 18, 2012ALIEASSIGNED TO LIE—
Jul 18, 2012GEANNOTIFICATION OF EXAMINER'S AMENDMENT/PRIORITY ACTION E-MAILED—
Jul 18, 2012GEAPEXAMINER'S AMENDMENT/PRIORITY ACTION E-MAILED—
Jul 18, 2012CPEAEXAMINERS AMENDMENT AND/OR PRIORITY ACTION - COMPLETED—
Jul 16, 2012DOCKASSIGNED TO EXAMINER—
Apr 12, 2012MPMKNOTICE OF PSEUDO MARK MAILED—
Apr 11, 2012NWOSNEW APPLICATION OFFICE SUPPLIED DATA ENTERED—
Apr 6, 2012NWAPNEW APPLICATION ENTERED—

Frequently asked questions

Related guidance