Drawing for FLEXENERGY

USPTO serial 90740435

FLEXENERGY

Reviewed by CopyMark Law Group

Reg. 8023763Status 700Registered
Filing date
Status date
Registration date
Nov 11, 2025
Examiner
MORRIS, KRISTINA KLOIBER
Law office
PUBLICATION AND ISSUE SECTION

What this means

Status 700 means the trademark is registered and active on the Principal Register. You have nationwide rights for the listed goods and services and may use ®. Section 8 maintenance is due between years five and six. Calendar Section 8 between years five and six, and consider trademark monitoring.

Status 700: Status 700 means the trademark is registered and active on the Principal Register. You have nationwide rights for the listed goods and services and may use ®. Section 8 maintenance is due between years five and six.

Need help with FLEXENERGY?

If you own this trademark, we can monitor new filings and help with USPTO deadlines. If you do not, we can file a new U.S. application.

Current trademark owner
Monitor this mark, or talk with CopyMark about this registration.
Not the owner?
File a new U.S. trademark application, or speak with our attorneys.

Owner

Attorney of record

The USPTO lists this attorney as the applicant's representative for correspondence on this application.

Stacie K. Smith

Stacie K. Smith FENNEMORE CRAIG, P.C.2394 EAST CAMELBACK ROADSUITE 600PHOENIX, AZ 85016-3429

Goods and services

ClassDescriptionStatusFirst use
037Technical support services, namely, technical advice related to the installation of turbines and heat exchange equipment; Technical support services, namely, technical advice related to the repair of turbines and heat exchange equipment; Repair, installation, tuning and maintenance of components, parts or systems in steam and gas turbine generators, power plants, power generating equipment, electricity generating equipment, combined heat and power equipment and boilers performed according to service contracts; Maintenance and repair of turbines and heat exchange equipment; Installation, maintenance and repair of components, parts or systems in steam and gas turbine generators, power plants, power generating equipment, electricity generating equipment, combined heat and power equipment and boilers; Maintenance, repair, replacement and tuning of components, parts or systems in steam and gas turbine generatorsACTIVE—
040Leasing of energy generating equipment in the nature of turbinesACTIVE—
041Training in the use and operation of turbines and heat exchange equipmentACTIVE—

Related trademarks

CopyMark links this record to cited §2(d) serials, the owner's other marks, Nice classes, similar mark names, and recently changed USPTO applications.

Prosecution history

DateCodeEventWhat it means
Nov 11, 2025NRCCNOTICE OF REGISTRATION CONFIRMATION EMAILED—
Nov 11, 2025R.PRREGISTERED-PRINCIPAL REGISTERYour trademark is registered on the Principal Register — the strongest form of federal trademark protection. You may use the ® symbol for the covered goods and services. Maintenance filings (Section 8 and renewals) are required to keep the registration alive.
Oct 21, 2025SUNANOTICE OF ACCEPTANCE OF STATEMENT OF USE E-MAILED—
Oct 21, 2025CNPRALLOWED PRINCIPAL REGISTER - SOU ACCEPTED—
Oct 20, 2025SUPCSTATEMENT OF USE PROCESSING COMPLETE—
Oct 17, 2025IUAFUSE AMENDMENT FILED—
Oct 17, 2025EISUTEAS STATEMENT OF USE RECEIVEDThe applicant filed a Statement of Use with specimens showing the mark in actual commerce. The USPTO will review the filing for compliance. If accepted, the mark can proceed to registration; if deficient, the USPTO may issue a requirement or office action.
Jul 31, 2025EXRANOTICE OF APPROVAL OF EXTENSION REQUEST E-MAILED—
Jul 30, 2025EX5GSOU EXTENSION 5 GRANTED—
Jul 30, 2025AITUCASE ASSIGNED TO INTENT TO USE PARALEGAL—
Apr 14, 2025EEXTSOU TEAS EXTENSION RECEIVEDThe applicant requested more time to file a Statement of Use before the Notice of Allowance deadline. Each extension typically adds six months. A limited number of extensions are available for intent-to-use applications not yet in use.
Apr 13, 2025EXT5SOU EXTENSION 5 FILED—
Oct 11, 2024EXRANOTICE OF APPROVAL OF EXTENSION REQUEST E-MAILED—
Oct 11, 2024EX4GSOU EXTENSION 4 GRANTED—
Oct 11, 2024EXT4SOU EXTENSION 4 FILED—
Oct 11, 2024EEXTSOU TEAS EXTENSION RECEIVEDThe applicant requested more time to file a Statement of Use before the Notice of Allowance deadline. Each extension typically adds six months. A limited number of extensions are available for intent-to-use applications not yet in use.
Apr 19, 2024EXRANOTICE OF APPROVAL OF EXTENSION REQUEST E-MAILED—
Apr 18, 2024EX3GSOU EXTENSION 3 GRANTED—
Apr 18, 2024EXT3SOU EXTENSION 3 FILED—
Apr 18, 2024EEXTSOU TEAS EXTENSION RECEIVEDThe applicant requested more time to file a Statement of Use before the Notice of Allowance deadline. Each extension typically adds six months. A limited number of extensions are available for intent-to-use applications not yet in use.
Sep 21, 2023EXRANOTICE OF APPROVAL OF EXTENSION REQUEST E-MAILED—
Sep 19, 2023EX2GSOU EXTENSION 2 GRANTED—
Sep 19, 2023EXT2SOU EXTENSION 2 FILED—
Sep 19, 2023EEXTSOU TEAS EXTENSION RECEIVEDThe applicant requested more time to file a Statement of Use before the Notice of Allowance deadline. Each extension typically adds six months. A limited number of extensions are available for intent-to-use applications not yet in use.
Apr 20, 2023EXRANOTICE OF APPROVAL OF EXTENSION REQUEST E-MAILED—
Apr 18, 2023EX1GSOU EXTENSION 1 GRANTED—
Apr 18, 2023EXT1SOU EXTENSION 1 FILED—
Apr 18, 2023EEXTSOU TEAS EXTENSION RECEIVEDThe applicant requested more time to file a Statement of Use before the Notice of Allowance deadline. Each extension typically adds six months. A limited number of extensions are available for intent-to-use applications not yet in use.
Oct 18, 2022NOAMNOA E-MAILED - SOU REQUIRED FROM APPLICANTA Notice of Allowance means your intent-to-use application cleared examination and opposition but is not registered yet. You must file a Statement of Use showing the mark in commerce, or request an extension, before the deadline — usually six months from the notice date.
Aug 24, 2022ASGNAUTOMATIC UPDATE OF ASSIGNMENT OF OWNERSHIP—
Aug 23, 2022NPUBOFFICIAL GAZETTE PUBLICATION CONFIRMATION E-MAILED—
Aug 23, 2022PUBOPUBLISHED FOR OPPOSITIONYour mark was published in the USPTO Official Gazette for a 30-day opposition window. During that period, third parties who believe they would be harmed can file an opposition. If no opposition is filed, prosecution usually continues toward registration or a Notice of Allowance.
Aug 3, 2022NONPNOTIFICATION OF NOTICE OF PUBLICATION E-MAILED—
Jul 21, 2022CNSAAPPROVED FOR PUB - PRINCIPAL REGISTER—
Jul 2, 2022TEMETEAS/EMAIL CORRESPONDENCE ENTERED—
Jul 1, 2022CRFACORRESPONDENCE RECEIVED IN LAW OFFICE—
Jul 1, 2022TROATEAS RESPONSE TO OFFICE ACTION RECEIVEDThis event means the applicant filed a response to a USPTO Office Action — typically arguments, amendments, or evidence addressing the examiner's objections. The USPTO will review the response and either allow the mark to proceed or issue another action.
Jun 15, 2022GNRNNOTIFICATION OF NON-FINAL ACTION E-MAILEDA non-final Office Action means the USPTO examining attorney has raised at least one issue with your trademark application but has not made a final decision. You usually have three months to respond with arguments, amendments, or evidence. Missing the deadline can abandon the application.
Jun 15, 2022GNRTNON-FINAL ACTION E-MAILEDA non-final Office Action means the USPTO examining attorney has raised at least one issue with your trademark application but has not made a final decision. You usually have three months to respond with arguments, amendments, or evidence. Missing the deadline can abandon the application.
Jun 15, 2022CNRTNON-FINAL ACTION WRITTENA non-final Office Action means the USPTO examining attorney has raised at least one issue with your trademark application but has not made a final decision. You usually have three months to respond with arguments, amendments, or evidence. Missing the deadline can abandon the application.
May 26, 2022TEMETEAS/EMAIL CORRESPONDENCE ENTERED—
May 26, 2022CRFACORRESPONDENCE RECEIVED IN LAW OFFICE—
May 26, 2022ALIEASSIGNED TO LIE—
May 19, 2022ERSITEAS RESPONSE TO SUSPENSION INQUIRY RECEIVED—
May 13, 2022RCCKSUSPENSION CHECKED - TO ATTORNEY FOR ACTION—
Jan 3, 2022DOCKASSIGNED TO EXAMINER—
Sep 24, 2021GNS3NOTIFICATION OF LETTER OF SUSPENSION E-MAILED—
Sep 24, 2021GNSLLETTER OF SUSPENSION E-MAILED—
Sep 24, 2021CNSLSUSPENSION LETTER WRITTEN—
Sep 17, 2021DOCKASSIGNED TO EXAMINER—
Aug 23, 2021NWOSNEW APPLICATION OFFICE SUPPLIED DATA ENTERED—
May 31, 2021NWAPNEW APPLICATION ENTERED—

Frequently asked questions

Related guidance